Photo-report: Preparatory works for pile cap concreting on Krestovsky Island

Photo-report: Preparatory works for pile cap concreting on Krestovsky Island. 

Currently the majority of bored piles with diameter of 1200 mm, depth – 42m are completed. Works are being implemented from temporary technological platforms filled from the costal part of Krestovsky Island (photo 1, 2). Sheet piles for the following excavations and construction of pile caps (photo 3, 4, 7) are being constructed inside the temporary technological platforms. 
From the South and North of Krestovsky Island up to Fairways technological flyovers are planned to be built for construction of the temporary technological platforms in the water area. One of subcontractors began its work at the Site (photo 10).